Road Work Full Closure at the North Split to begin in one week

Dear All,

While there is a lot of information below, this is the latest that I have received from INDOT (Indiana Department of Transportation) about the north split closure that is scheduled to start on Saturday, May 15th. I thought that it was worthwhile in making sure as many people as possible see this, as it is going to be a long, involved project. Remember, even if you do not travel through Indianapolis on I-65 or I-70, this still may affect you as traffic will be heavier on I-465 since those who normally go through downtown will most likely be going around the city to get to destinations. See the information below to learn details or go to northsplit.com. I do hope that this information is helpful as you drive to where you need to go. I will also try to keep updated information on my web page at “Janice McHenry – Former City-County Councillor”.

Sincerely,

Janice McHenry
Full Closure at the North Split to begin in one week
Vermont Street will also close with start of North Split construction

 

FOR IMMEDIATE RELEASE
May 7, 2021

MARION COUNTY, Ind. – The Indiana Department of Transportation (INDOT) reminds motorists the 18-month closure of the North Split Interchange in downtown Indianapolis is only one week away. Major reconstruction is expected to close the I-65/I-70 southbound lanes between the North Split and Washington Street on or after May 15 with the full closure of the interchange expected May 16, weather permitting.

During the full closure, I-65 and I-70 between the North Split and Washington Street will be closed to all traffic while bridges and roadways are reconstructed. However, access in and out of downtown will remain via the I-70 westbound exit ramp to Michigan or Ohio streets and the Pine Street entrance ramp to I-70 eastbound. In addition, the I-65 southbound to I-70 eastbound and I-70 westbound to I-65 northbound connections will remain open to traffic during construction.

Currently, the Michigan Street exit is closed for reconstruction, while the Ohio and Fletcher Street exits remain open.

In addition to the North Split closure, beginning on or after Monday, May 17, Vermont Street between Davidson and Pine streets will be closed to vehicular and pedestrian traffic while the bridges over Vermont Street are demolished as part of the North Split project. The Vermont St. work is estimated to be completed on or after May 31. During this local closure, eastbound traffic will be detoured to New York Street and westbound traffic will be detoured to Michigan Street.

Project information can be found at northsplit.com.

To help drivers prepare for the upcoming closure of the North Split, below is an overview of the interstate impacts and how travel will be maintained throughout construction.

I-70 westbound:

Will remain open at the Keystone interchange
Will remain open to I-65 northbound
Will remain open to either the Michigan or Ohio Street exits via collector/distributor
Will be accessible from Washington Street entrance ramp
Will be closed to I-70 westbound through traffic and to I-65 southbound
I-70 eastbound:

Will be accessible from Pine Street entrance ramp. (There will be detours as the Michigan Street, New York Street and Vermont Street bridges are reconstructed, but the Pine Street entrance ramp onto I-70 eastbound will remain open.)
From the airport, all exits remain open for eastbound traffic up to Washington Street
The West, Illinois and Meridian Street interchanges (south side) can access I-65 southbound and I-65 northbound to Washington Street
Will be closed to I-70 eastbound through traffic and to I-65 northbound
I-65 northbound:

Will be accessible from the North Illinois Street onramp
Will remain open through the South Split up to the Washington Street exit
Will be closed to I-65 northbound through traffic and to I-70 westbound
I-65 southbound:

Will remain open to I-70 eastbound (except closed for 45 days in Fall 2021)
Will be accessible from the West Street entrance ramp to I-70 eastbound only (except closed for 45 days in Fall 2021)
Will be accessible from the Delaware Street entrance ramp to I-70 eastbound only (except closed for 45 days in Fall 2021)
Will be accessible from the Washington Street entrance ramp
Local streets crossing under the interstate will be closed for overhead construction work – durations vary.

For up-to-date project information, visit Northsplit.com or text “NORTHSPLIT” to 468311. Follow the North Split project’s progress on social media at:

Facebook: Facebook.com/NorthSplit
Twitter: @NorthSplit
Instagram: @IndyNorthSplit
Stay informed
Indiana motorists can monitor road closures, road conditions, and traffic alerts any time throughout the state, here: https://www.in.gov/indot/2420.htm.

For details on the lane restrictions and closures associated with the current work, please visit 511 Cars for more information.

About the Indiana Department of Transportation
Over the past 100 years, INDOT has transformed the state of Indiana into the Crossroads of America we know today. With six district offices and 3,500 employees, the agency is responsible for constructing and maintaining more than 29,000 lane miles of highways, more than 5,700 bridges, and supporting 4,500 rail miles and 117 airports across the state. Indiana once again ranked #1 in the U.S. for infrastructure in CNBC’s 2019 “America’s Top States for Business” ranking. Learn more about INDOT at in.gov/indot.

Customer Service – Have a question or comment? Contact INDOT’s Next Level Customer Service Center using any of the following methods:
1-855-INDOT4U (1-855-463-6848)
indot4u.com
indot@indot.IN.gov

Media Contact
Mallory Duncan
317-452-2369
maduncan@indot.in.gov

NS Closure_mid-May 2021
Vermont Street Detour NS e-newsletter
footer

North Split closure begins in one week, Vermont to close May 17

North Split
Header
8 Day
Countdown
Full Closure at the North Split to Begin Next Weekend
The 18-month closure of the North Split Interchange in downtown Indianapolis is only one week away. Major reconstruction is expected to begin closing the interchange on or after May 15, 2021, weather permitting.

During the full closure, I-65 and I-70 between the North Split and Washington Street will be closed to all traffic while bridges and roadways are reconstructed. However, access in and out of downtown will remain.

Motorists are encouraged to start mapping alternate routes now. Those who will continue to drive can see detour maps at northsplit.com/maps. Those who want to investigate ride sharing or alternate modes of transportation can visit our partners at Commuter Connect at commuterconnect.us.

Vermont Scheduled to Close May 17
While crews demolish the overhead interstate bridges, Vermont Street will be closed. That closure is expected to begin on or after May 17 and continue until the end of the month.

Eastbound traffic will be detoured to New York Street and westbound traffic will be detoured to Michigan Street.

Vermont St
detour
Bridge over
Saint Clair
Work on I-65 C/D Ramp to Michigan St. Continues
Crews are currently installing the MSE wall, rebar and bridge deck on the I-65 southbound collector/distributor ramp over Saint Clair Street. The ramp is expected to reopen in mid-June.

Full Closure at the North Split to begin in one week

Vermont Street will also close with start of North Split construction

 

FOR IMMEDIATE RELEASE
May 7, 2021

MARION COUNTY, Ind. – The Indiana Department of Transportation (INDOT) reminds motorists the 18-month closure of the North Split Interchange in downtown Indianapolis is only one week away. Major reconstruction is expected to close the I-65/I-70 southbound lanes between the North Split and Washington Street on or after May 15 with the full closure of the interchange expected May 16, weather permitting.

During the full closure, I-65 and I-70 between the North Split and Washington Street will be closed to all traffic while bridges and roadways are reconstructed. However, access in and out of downtown will remain via the I-70 westbound exit ramp to Michigan or Ohio streets and the Pine Street entrance ramp to I-70 eastbound. In addition, the I-65 southbound to I-70 eastbound and I-70 westbound to I-65 northbound connections will remain open to traffic during construction.

Currently, the Michigan Street exit is closed for reconstruction, while the Ohio and Fletcher Street exits remain open.

In addition to the North Split closure, beginning on or after Monday, May 17, Vermont Street between Davidson and Pine streets will be closed to vehicular and pedestrian traffic while the bridges over Vermont Street are demolished as part of the North Split project. The Vermont St. work is estimated to be completed on or after May 31. During this local closure, eastbound traffic will be detoured to New York Street and westbound traffic will be detoured to Michigan Street.

Project information can be found at northsplit.com.

To help drivers prepare for the upcoming closure of the North Split, below is an overview of the interstate impacts and how travel will be maintained throughout construction.

I-70 westbound:

  • Will remain open at the Keystone interchange
  • Will remain open to I-65 northbound
  • Will remain open to either the Michigan or Ohio Street exits via collector/distributor
  • Will be accessible from Washington Street entrance ramp
  • Will be closed to I-70 westbound through traffic and to I-65 southbound

I-70 eastbound:

  • Will be accessible from Pine Street entrance ramp. (There will be detours as the Michigan Street, New York Street and Vermont Street bridges are reconstructed, but the Pine Street entrance ramp onto I-70 eastbound will remain open.)
  • From the airport, all exits remain open for eastbound traffic up to Washington Street
  • The West, Illinois and Meridian Street interchanges (south side) can access I-65 southbound and I-65 northbound to Washington Street
  • Will be closed to I-70 eastbound through traffic and to I-65 northbound

I-65 northbound:

  • Will be accessible from the North Illinois Street onramp
  • Will remain open through the South Split up to the Washington Street exit
  • Will be closed to I-65 northbound through traffic and to I-70 westbound

I-65 southbound:

  • Will remain open to I-70 eastbound (except closed for 45 days in Fall 2021)
  • Will be accessible from the West Street entrance ramp to I-70 eastbound only (except closed for 45 days in Fall 2021)
  • Will be accessible from the Delaware Street entrance ramp to I-70 eastbound only (except closed for 45 days in Fall 2021)
  • Will be accessible from the Washington Street entrance ramp

Local streets crossing under the interstate will be closed for overhead construction work – durations vary.

For up-to-date project information, visit Northsplit.com or text “NORTHSPLIT” to 468311. Follow the North Split project’s progress on social media at:

Stay informed
Indiana motorists can monitor road closures, road conditions, and traffic alerts any time throughout the state, here: https://www.in.gov/indot/2420.htm.

For details on the lane restrictions and closures associated with the current work, please visit 511 Cars for more information.

About the Indiana Department of Transportation
Over the past 100 years, INDOT has transformed the state of Indiana into the Crossroads of America we know today. With six district offices and 3,500 employees, the agency is responsible for constructing and maintaining more than 29,000 lane miles of highways, more than 5,700 bridges, and supporting 4,500 rail miles and 117 airports across the state. Indiana once again ranked #1 in the U.S. for infrastructure in CNBC’s 2019 “America’s Top States for Business” ranking. Learn more about INDOT at in.gov/indot.

Customer Service – Have a question or comment? Contact INDOT’s Next Level Customer Service Center using any of the following methods:
1-855-INDOT4U (1-855-463-6848)
indot4u.com
indot@indot.IN.gov

Media Contact
Mallory Duncan
317-452-2369
maduncan@indot.in.gov


NS Closure_mid-May 2021


Vermont Street Detour NS e-newsletter
              footer

North Split closure begins in one week, Vermont to close May 17