I wanted to share with all of you the information I received about work that is being done by INDOT (Indiana Department of Transportation) not only in our immediate area, but also throughout Marion County and off of I – 65 in Boone County.  As always, projects can be affected by the weather – however, overall it looks like it will be a nice weekend.  Hope you have a great weekend and that if you are planning on traveling on the interstates this is helpful in your driving.  Please feel free to forward this information on to others , not only in District 6, but to anyone who may be driving on I – 465 or I – 65 in these areas.
 
Sincerely,
 
Janice McHenry
City-County Councillor District 6
Full closures, detours and other lane restrictions

Having trouble viewing this email? View it as a Web page.

Traffic Alert header

Weekend Work: Construction Around Marion County

July 12 to July 15

INDIANAPOLIS – The Indiana Department of Transportation will continue work in Marion County this weekend.

Five projects will be working simultaneously in Marion County throughout the weekend, weather permitting.

Please watch @INDOTEast on Twitter for weather-related cancellations or changes.

INDOT would like to remind people to plan extra time this weekend to drive to their destination and watch for slow traffic in construction zones.

Full closures

  • I-65 SB from I-865 to I-465
    • ALL LANES CLOSED
    • Closure begins Friday at 9 p.m.
    • Opens Monday, July 29th by 6 a.m.
    • Detour: Take I-865 EB to I-465 SB back to I-65 SB
  • I-65 SB from South Split to I-465
    • ALL LANES CLOSED
    • Closure begins Friday at 7 p.m.
    • Opens Monday, July 22nd by 3 p.m.
  • I-65 SB from North Split to South Split
    • ALL LANES CLOSED
    • Closure begins Friday at 9 p.m.
    • Opens Monday, July 15th by 6 a.m.
    • Detour: Take I-70 EB to I-465 SB back to I-65 SB if coming from the north. Or get on I-70 WB from downtown and take I-70 WB to I-465 EB/SB back to I-65 SB.

Lane restrictions

  • I-65 SB from I-465 to Southport Rd
    • Left three lanes closed
    • Friday at 9 p.m. to Monday at 6 a.m.
  • I-69 NB from 75th Street to S.R. 37
    • Left three lanes closed
    • Friday at 8 p.m. to Saturday at 9 a.m.
  • I-69 SB from 116th Street to 75th Street
    • Left three lanes closed
    • Friday at 7 p.m. to Monday at 6 a.m.
  • I-465 EB from Keystone to Pendleton Pike
    • Left three lanes closed
    • Friday 7 p.m. to Monday at 6 a.m.
  • I-465 WB from Fall Creek to the White River
    • Left three lanes closed
    • Friday 7 p.m. to Monday at 6 a.m.
  • I-65 SB from I-465 to Kessler Blvd
    • Left two lanes closed
    • Friday 9 p.m. to Monday, July 22 at 5 a.m.
  • I-65 NB from Little Eagle Creek to 56th Street
    • Right two lanes closed
    • Friday at 9 p.m. to Monday at 6 a.m.
    • RAMPS: I-65 NB to Lafayette Rd CLOSED, Lafayette Rd to I-65 NB CLOSED
  • I-65 NB from 29th Street to Martin Luther King Jr. St.
    • Left two lanes closed
    • Friday at 9 p.m. to Monday a 6 a.m.
  • I-465 NB from 71st Street to 96th Street
    • Left four lanes closed
    • Friday at 8 p.m. to Sunday at 9 p.m.

weekend closures 7-12

Stay informed

Follow @INDOTEast on TwitterFacebook and Instagram.

Subscribe to receive text and email alerts about INDOT projects and services at alerts.indot.in.gov.

Learn about highway work zones and other traffic alerts at indot.carsprogram.org, 1-800-261-ROAD (7623) or 511 from a mobile phone.

Next Level Roads

Updated ramp closures on I-65 in Boone County

BOONE COUNTY, Ind. – The Indiana Department of Transportation announces the updated schedule for ramp closures on I-65 in Boone County. Below is the following schedule for resurfacing the ramps at Exit 130, weather permitting:

• Whitestown Parkway on ramp to I-65 southbound closing Monday, July 15 from 6 p.m. to
6 a.m. on Tuesday.
• Whitestown Parkway on ramp to I-65 southbound closing Tuesday, July 16 from 6 p.m. to
6 a.m. on Wednesday.
• I-65 southbound exit ramp to Whitestown Parkway closing Wednesday, July 17 from 6 p.m. to 6 a.m. Thursday
• Whitestown Parkway on ramp to I-65 northbound closing Thursday, July 18 from 6 p.m. to 6 a.m. Friday

This project was awarded to Rieth-Riley Construction for $13.8 million. This project also included resurfacing I-65 from one and one half miles south of State Road 39 to just north of I-865.

This project is scheduled for completion at the end of August.